During a site inspection, the architect observes a discrepancy between the specified material and the installed material. <br>
What is the architect's most appropriate next step?
-
A
Stop the work immediately.
-
B
Issue a change order to use the installed material.
-
C
Notify the contractor and request clarification.
-
D
Document the observation in the site report and inform the owner.