An Agile team has a very large and detailed product backlog where items planned for six months from now have the same level of detail as items for the upcoming sprint. Which characteristic of a DEEP backlog is this team MOST likely violating?
-
A
Estimated
-
B
Emergent
-
C
Detailed Appropriately
-
D
Prioritized