An Agile team is holding a Sprint Review to demonstrate a working increment of their product. A stakeholder comments that while a feature was built exactly according to the user story's acceptance criteria, it doesn't solve the underlying business problem effectively. This feedback is PRIMARILY a validation of what?
-
A
The team's velocity and capacity planning.
-
B
The technical quality and performance of the code.
-
C
The alignment between the delivered solution and the actual business need.
-
D
The accuracy of the initial project budget.