A Scrum Master observes that the Developers are consistently struggling to meet their Sprint Goals. Upon investigation, they find that the team is frequently interrupted by requests from stakeholders for new features. Which of the following is the MOST effective action for the Scrum Master to take?
-
A
Tell the Developers to work longer hours to accommodate the stakeholder requests.
-
B
Coach the Product Owner on techniques for stakeholder management and Product Backlog prioritization.
-
C
Remove the stakeholders' access to the Developers during the Sprint.
-
D
Cancel the Sprint and start a new one that includes the stakeholders' requests.