A maintenance planner is faced with a large number of incoming work orders of varying urgency. To ensure that the most critical work is addressed first in a consistent and objective manner, what is the BEST tool to implement?
-
A
The personal judgment of the maintenance supervisor.
-
B
A formal priority system based on risk and criticality (e.g., RIME index).
-
C
A "first-in, first-out" (FIFO) system.
-
D
The request date from the operations department.