A maintenance technician plans to replace a faulty valve on a compressed air line. According to standard safety procedures, what is the primary purpose of applying a lock and tag to the main air supply shutoff valve before starting the work?
-
A
To inform the production supervisor that maintenance is being performed.
-
B
To prevent the unexpected re-energization of the system while it is being serviced.
-
C
To track the amount of time the equipment is out of service for maintenance.
-
D
To ensure the correct replacement valve is ordered from the storeroom.