A maintenance and reliability manager is preparing a business case to secure funding for a new predictive maintenance program. To align with the organization's strategic objectives and gain executive buy-in, which of the following is the most critical element to include in the presentation?
-
A
A detailed list of all the new sensor technologies to be purchased.
-
B
A technical comparison of various CMMS software options.
-
C
An analysis showing the projected Return on Investment (ROI) and impact on Overall Equipment Effectiveness (OEE).
-
D
A benchmark report of competitor maintenance spending.