During the execution of a construction project, the owner requests a significant change to the flooring material in a large section of the building, which was not part of the original contract. What is the most appropriate first step for the Construction Manager to take?
-
A
Issue a Construction Change Directive (CCD) to the contractor to proceed with the work immediately to avoid delays.
-
B
Document the owner's request and prepare a formal Change Order detailing the scope, cost, and schedule impacts for all parties to review and approve.
-
C
Verbally agree to the change with the contractor and owner to maintain a good working relationship and sort out the details later.
-
D
Reject the request as it deviates from the signed contract documents and could lead to disputes.