A construction manager is analyzing a project's performance and finds that the Cost Performance Index (CPI) is 0.90 and the Schedule Performance Index (SPI) is 1.10. Which of the following statements accurately interprets these values?
-
A
The project is over budget and behind schedule.
-
B
The project is under budget and ahead of schedule.
-
C
The project is over budget and ahead of schedule.
-
D
The project is under budget and behind schedule.