A test manager is preparing a Test Summary Report for stakeholders after a major test cycle. Which of the following elements is MOST crucial to include to provide a clear assessment of product readiness?
-
A
A detailed log of every test case executed and the time it took.
-
B
An evaluation of the test items against the defined exit criteria.
-
C
A list of all testers involved in the execution phase and their individual pass/fail rates.
-
D
The complete set of test scripts used for automated testing.