A development team consistently underestimates stories by 30-40%. Which technique would BEST help them improve estimation accuracy over time?
-
A
Track velocity trends and use historical data to calibrate future estimates
-
B
Assign estimation responsibility to the most senior developer only
-
C
Double all estimates to create a safety buffer
-
D
Replace story points with exact hour-based estimates