A development team consistently misses sprint goals because members work in silos without communicating dependencies. What is the most effective first step to address this?
-
A
Assign a project manager to track all dependencies
-
B
Implement daily stand-ups focused on identifying and resolving blockers
-
C
Reduce the number of stories committed to each sprint
-
D
Create a detailed dependency matrix before each sprint