During sprint planning, the team discovers that a high-priority user story has unclear acceptance criteria. What is the most appropriate action?
-
A
Begin development and clarify criteria during the sprint
-
B
Send the story back to the product owner for refinement before committing
-
C
Estimate the story with extra buffer time to account for unknowns
-
D
Skip the story and move to the next sprint