An architect completes the Design Development phase, and the updated cost estimate indicates the project is 15% over the owner's budget for the Cost of the Work. According to AIA B101-2017, what is the architect's primary responsibility in this situation?
-
A
Immediately halt all work until the owner secures additional funding.
-
B
Propose reasonable adjustments to the project's scope, quality, or budget, and obtain the owner's approval.
-
C
Proceed with Construction Documents while advising the owner to increase the construction contingency.
-
D
Absorb the cost of any redesign required to bring the project back within the original budget.