During project execution, the client verbally requests a significant change to the window specifications, which were clearly defined in the construction documents. According to AIA B101, what is the architect's most appropriate initial action?
-
A
Instruct the contractor to proceed with the change to maintain the project schedule.
-
B
Document the request and advise the client that a written change order is required before proceeding.
-
C
Reject the request as it deviates from the signed contract documents.
-
D
Approve the change and adjust the architect's fees accordingly to cover the additional work.