A business analyst on an agile team notices that a planned feature no longer aligns with the current market conditions. What principle should guide their next action?
-
A
Stick to the original plan to maintain consistency
-
B
Welcome changing requirements, even late in development
-
C
Defer all decisions to the product owner
-
D
Freeze the backlog until the next sprint planning