A Nutanix project manager wants to identify which tasks must be completed on time to avoid delaying the overall project. Which analysis should be performed?
-
A
Monte Carlo simulation
-
B
Critical path analysis
-
C
Pareto analysis
-
D
Fishbone diagram analysis