Nutanix Exam Project Planning & Execution 5 — Questions and Answers
Question 1: A Nutanix project manager wants to identify which tasks must be completed on time to avoid delaying the overall project. Which analysis should be performed?
- Monte Carlo simulation
- Critical path analysis (Correct answer)
- Pareto analysis
- Fishbone diagram analysis
Correct answer: Critical path analysis
Critical path analysis identifies the sequence of tasks with zero float, meaning any delay directly impacts the project completion date.
Question 2: Which Nutanix licensing model requires project planners to account for socket-based pricing when budgeting a new cluster?
- Nutanix Cloud Clusters (NC2)
- Nutanix NX on-premises hardware with per-socket licensing (Correct answer)
- Nutanix Calm SaaS subscription
- Nutanix Files capacity-based licensing
Correct answer: Nutanix NX on-premises hardware with per-socket licensing
On-premises NX hardware uses per-socket licensing, so the number of CPU sockets per node directly drives software licensing costs.
Question 3: A project team completes Nutanix node imaging ahead of schedule but the network switch configuration is delayed. What project management concept does this illustrate?
- Schedule compression
- Resource over-allocation
- Task dependency causing a bottleneck (Correct answer)
- Scope creep
Correct answer: Task dependency causing a bottleneck
The node imaging task cannot fully benefit the project because downstream tasks depend on the network switch configuration being ready.
Question 4: During project closure for a Nutanix deployment, which activity formally releases the project team and confirms deliverable acceptance?
- Risk register update
- Formal sign-off and project closeout report (Correct answer)
- Sprint retrospective
- Change request submission
Correct answer: Formal sign-off and project closeout report
Project closeout includes obtaining formal stakeholder acceptance of deliverables and releasing the team from project obligations.
Question 5: A Nutanix implementation project is using an Agile approach. Which artifact best tracks the remaining work to be completed in a sprint?
- Gantt chart
- Sprint burndown chart (Correct answer)
- Network diagram
- Risk matrix
Correct answer: Sprint burndown chart
A sprint burndown chart tracks remaining story points or tasks over the sprint timeline, showing whether the team is on pace to complete the sprint.
Question 6: What is the recommended first step when onboarding a new team member to an in-progress Nutanix infrastructure project?
- Assign them to the most critical task immediately
- Review the project charter, current schedule, and risk register with them (Correct answer)
- Have them attend the next client meeting without preparation
- Ask them to rewrite the project plan
Correct answer: Review the project charter, current schedule, and risk register with them
Reviewing foundational project documents ensures the new member understands scope, status, and risks before contributing.
Question 7: A Nutanix project manager is forecasting the Estimate at Completion (EAC) assuming future work will be performed at the current CPI of 0.85. Which formula applies?
- EAC = BAC - EV
- EAC = AC + (BAC - EV) / CPI (Correct answer)
- EAC = PV + AC
- EAC = BAC × SPI
Correct answer: EAC = AC + (BAC - EV) / CPI
When future performance is expected to mirror current efficiency, EAC = AC + (BAC - EV) / CPI is the appropriate forecast formula.
A Nutanix project manager wants to identify which tasks must be completed on time to avoid delaying the overall project.
Which analysis should be performed?