Nutanix Exam Project Planning & Execution 4

Free ยท Instant Results

A Nutanix project has a Budget at Completion (BAC) of $500,000. At the midpoint, EV = $200,000 and AC = $250,000. What is the Cost Performance Index (CPI)?