Nutanix Exam Project Planning & Execution 4 — Questions and Answers
Question 1: A Nutanix project has a Budget at Completion (BAC) of $500,000. At the midpoint, EV = $200,000 and AC = $250,000. What is the Cost Performance Index (CPI)?
- 0.80 (Correct answer)
- 1.25
- 0.50
- 1.00
Correct answer: 0.80
CPI = EV / AC = $200,000 / $250,000 = 0.80, indicating the project is over budget for work completed.
Question 2: Which communication planning element ensures that the right Nutanix project stakeholders receive information at the appropriate frequency?
- RACI matrix
- Communications management plan (Correct answer)
- Work breakdown structure
- Quality management plan
Correct answer: Communications management plan
The communications management plan defines what information is shared, with whom, how often, and through which channels.
Question 3: A Nutanix deployment team is distributed across three time zones. Which execution strategy best maintains coordination?
- Assign all work to one time zone only
- Establish overlapping work hours and daily async stand-up updates (Correct answer)
- Eliminate all meetings to avoid conflict
- Delay non-critical tasks until teams are co-located
Correct answer: Establish overlapping work hours and daily async stand-up updates
Overlapping hours and asynchronous updates balance real-time collaboration with the constraints of distributed teams.
Question 4: In Nutanix project planning, what does a RACI matrix define?
- Server rack installation sequence
- Roles and responsibilities for each project task (Correct answer)
- Risk likelihood and impact scores
- Cost allocation by department
Correct answer: Roles and responsibilities for each project task
A RACI matrix identifies who is Responsible, Accountable, Consulted, and Informed for each project activity.
Question 5: A Nutanix Prism Central upgrade is planned as part of a larger infrastructure project. Why should this task be placed on the critical path?
- Because it is the most expensive task
- Because downstream cluster management tasks depend on its completion (Correct answer)
- Because it involves the most team members
- Because it is the first task assigned
Correct answer: Because downstream cluster management tasks depend on its completion
Prism Central must be upgraded before dependent management tasks can proceed, making it a critical dependency on the project path.
Question 6: What is the purpose of a project baseline in a Nutanix HCI deployment?
- To record initial hardware inventory
- To provide an approved reference for scope, schedule, and cost against which performance is measured (Correct answer)
- To document network IP address assignments
- To list all software licenses purchased
Correct answer: To provide an approved reference for scope, schedule, and cost against which performance is measured
A project baseline is the approved snapshot of scope, schedule, and cost used to measure and report project performance variance.
Question 7: During a Nutanix cluster migration, a key stakeholder requests a change that would delay the go-live date by three weeks. The project manager should:
- Immediately implement the change to satisfy the stakeholder
- Evaluate the change impact, update the change log, and present options to the steering committee (Correct answer)
- Refuse the change outright to protect the schedule
- Implement the change secretly without updating the schedule
Correct answer: Evaluate the change impact, update the change log, and present options to the steering committee
All changes must be evaluated for impact and reviewed by the appropriate authority before approval or rejection.
A Nutanix project has a Budget at Completion (BAC) of $500,000.
At the midpoint, EV = $200,000 and AC = $250,000.
What is the Cost Performance Index (CPI)?