During a Nutanix cluster deployment project, the project manager identifies that a key engineer is unavailable for two weeks mid-project. Which risk response strategy is most appropriate?
-
A
Accept the risk and proceed
-
B
Transfer the risk to a vendor
-
C
Mitigate by cross-training another team member in advance
-
D
Avoid the risk by canceling the project