Nutanix Exam Project Planning & Execution 2 — Questions and Answers
Question 1: During a Nutanix cluster deployment project, the project manager identifies that a key engineer is unavailable for two weeks mid-project. Which risk response strategy is most appropriate?
- Accept the risk and proceed
- Transfer the risk to a vendor
- Mitigate by cross-training another team member in advance (Correct answer)
- Avoid the risk by canceling the project
Correct answer: Mitigate by cross-training another team member in advance
Cross-training a backup resource mitigates the risk of personnel unavailability before it impacts the schedule.
Question 2: A Nutanix implementation project has reached 60% completion but scope has expanded significantly. What should the project manager do first?
- Implement all new scope immediately
- Submit a formal change request for review and approval (Correct answer)
- Ignore the new scope until project closure
- Restart the project with updated scope
Correct answer: Submit a formal change request for review and approval
All scope changes should go through a formal change control process to assess impact on cost, schedule, and resources.
Question 3: Which Nutanix tool provides real-time capacity forecasting to help project planners determine future infrastructure needs?
- Nutanix Calm
- Prism Central capacity runway (Correct answer)
- Nutanix Flow
- Nutanix Files
Correct answer: Prism Central capacity runway
Prism Central's capacity runway feature analyzes current consumption trends to forecast when resources will be exhausted.
Question 4: A project team is deploying Nutanix across three data centers simultaneously. What scheduling technique best manages interdependencies between site deployments?
- Critical Path Method (CPM) (Correct answer)
- Agile sprints with no dependencies
- Resource leveling only
- Fast-tracking all tasks
Correct answer: Critical Path Method (CPM)
CPM identifies the longest sequence of dependent tasks, helping managers focus on activities that directly impact the project end date.
Question 5: During a Nutanix HCI project kickoff, stakeholders disagree on success criteria. What document should the project manager produce to resolve this?
- Risk register
- Project charter with defined acceptance criteria (Correct answer)
- Lessons learned log
- Network topology diagram
Correct answer: Project charter with defined acceptance criteria
The project charter formally documents objectives, scope, and acceptance criteria, aligning stakeholder expectations from the start.
Question 6: A Nutanix cluster node fails during user acceptance testing (UAT). How should the project manager classify this event?
- A project risk that has now become an issue (Correct answer)
- A lessons learned item only
- A change request to close UAT early
- An accepted project constraint
Correct answer: A project risk that has now become an issue
When a risk event actually occurs, it transitions from a risk (potential) to an issue (actual problem) that must be actively managed.
Question 7: Which Earned Value metric indicates whether a Nutanix deployment project is behind schedule when its value is less than 1.0?
- Cost Performance Index (CPI)
- Schedule Performance Index (SPI) (Correct answer)
- Budget at Completion (BAC)
- Estimate to Complete (ETC)
Correct answer: Schedule Performance Index (SPI)
SPI = EV / PV; a value below 1.0 means less work has been completed than planned, indicating a schedule delay.
During a Nutanix cluster deployment project, the project manager identifies that a key engineer is unavailable for two weeks mid-project.
Which risk response strategy is most appropriate?