In earned value management, a CPI of 0.85 indicates the project is:
Answer: Over budget
CPI below 1.0 means each dollar spent earns less than a dollar of value, so over budget.
EV is $40,000, PV is $50,000, and AC is $45,000. What is the schedule variance (SV)?
Answer: −$10,000
SV = EV − PV = 40,000 − 50,000 = −$10,000, meaning behind schedule.
Which risk response involves shifting the impact of a threat to a third party, such as through insurance?
Answer: Transfer
Transfer moves the impact and ownership of a risk to a third party, often via contract or insurance.
What does a RACI matrix clarify?
Answer: Roles and responsibilities for activities
RACI maps who is Responsible, Accountable, Consulted, and Informed for each activity.
Which dependency type means a successor cannot start until its predecessor finishes?
Answer: Finish-to-start
Finish-to-start is the most common logical relationship between activities.
A project manager holds a meeting at the end of each phase to capture what went well and what did not. This is:
Answer: Lessons learned review
Lessons learned sessions capture knowledge for use in future phases and projects.
Which is a characteristic of a project, as opposed to ongoing operations?
Answer: Temporary with a defined start and end
Projects are temporary endeavors that create a unique product, service, or result.
How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy
Sources & references
Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy
- npscerts.com — Test delivery, eligibility, fees, exam format, passing score, renewal, score release, time limit, score validity · verified Oct 2026