During transformer commissioning, what is the primary purpose of performing a turns ratio test?
-
A
Verify insulation resistance between windings
-
B
Confirm the transformer ratio matches nameplate data within acceptable tolerance
-
C
Measure winding resistance to detect shorted turns
-
D
Check for partial discharge activity under load