During transformer commissioning, what is the primary purpose of performing a turns ratio test?
Select your answer
A
Verify insulation resistance between windings
B
Confirm the transformer ratio matches nameplate data within acceptable tolerance
C
Measure winding resistance to detect shorted turns
D
Check for partial discharge activity under load