Risk Assessment Flashcards
6 cards from real NEBOSH practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 6 Risk Assessment flashcards as text
What is the purpose of a 'baseline risk assessment' on a new site?
Answer: To identify all hazards present before work begins, establishing the initial risk picture to guide the safety plan and method statements
A baseline (initial) risk assessment surveys the entire project or workplace before work commences to identify all foreseeable hazards, establish a starting risk profile, and inform the safety plan, site-specific rules, induction content, and method statements for all subsequent activities.
How is risk assessment applied to 'lone working'?
Answer: Lone worker risk assessment must consider: isolation (no immediate help available), nature of work (high-risk tasks may be prohibited alone), communication systems, check-in procedures, and emergency response arrangements
Lone workers (those working alone or without close supervision) face additional risks because help is not immediately available if they are injured, assaulted, or incapacitated. Risk assessment must evaluate: the nature of tasks (prohibiting high-risk tasks alone), communication methods (phone, check-in apps), and emergency response procedures.
What is 'SFAIRP' and how does it relate to ALARP?
Answer: So Far As Is Reasonably Practicable — equivalent to ALARP in the UK context; both require that risk be reduced as much as is reasonably practicable
SFAIRP ('so far as is reasonably practicable') and ALARP ('as low as reasonably practicable') represent the same legal standard in UK and many Gulf jurisdictions — risk must be reduced as far as reasonably practicable, weighing the risk against the sacrifice (time, cost, trouble) required. If cost is grossly disproportionate to benefit, the measure may not be required.
What specific risk assessment is required before excavation work on a construction site?
Answer: Assessment of: underground services (electricity, gas, water), ground stability, atmosphere in deep excavations, materials storage loads, and water ingress/flooding risk
Excavation risk assessments must address: underground utility services (location and isolation), ground conditions (stability, shoring requirements), adjacent structures and loads (surcharge), atmospheric hazards in deep excavations, flooding/groundwater, and access/egress. Striking buried services is a major cause of fatal injuries in Gulf construction.
How should risk assessment address language barriers in a multilingual Gulf construction workforce?
Answer: Risk assessments, method statements, and safety communications should be translated into workers' languages, supplemented with visual aids (pictograms), and include verification of understanding
Gulf construction sites employ workers from South Asia, Southeast Asia, and Africa who may not understand English or Arabic. Risk assessment outputs, SWMS, and safety communication must be accessible in workers' languages, using translated documents, pictograms, visual demonstrations, and toolbox talks in their native language. Failure to communicate creates documented legal liability.
What is the role of the 'Construction Phase Plan' in managing risks on Gulf construction projects?
Answer: The CPP is a project-specific document outlining significant risks, control measures, emergency procedures, site rules, and H&S management arrangements for the entire construction phase
The Construction Phase Plan (CPP), required under UK CDM Regulations and equivalent Gulf construction safety regulations (UAE, Qatar, Saudi), documents: site-specific hazards, risk control arrangements, emergency procedures, welfare facilities, and site rules. It is a living document updated as the project progresses and new risks emerge.