In the NC Merger process, what does Concurrence Point 3 select?
Answer: The Least Environmentally Damaging Practicable Alternative (LEDPA) / preferred alternative
Concurrence Point 3 is where Merger team agencies agree on the LEDPA, which becomes the preferred alternative.
Federal regulations require a value engineering analysis for federal-aid projects on the National Highway System above what estimated total cost?
Answer: $50 million
Federal law requires value engineering on NHS projects with a total estimated cost of $50 million or more (the threshold for bridge projects is $40 million).
Which federal requirement means the steel and iron permanently built into a federal-aid highway project must generally be made in the United States?
Answer: Buy America
Buy America provisions require domestic steel and iron (and other covered materials) on federal-aid projects unless a waiver applies.
What is the main goal of the Disadvantaged Business Enterprise (DBE) program on NCDOT federal-aid contracts?
Answer: Give socially and economically disadvantaged small businesses a fair chance to compete
The DBE program sets contract goals so that qualified small disadvantaged firms can compete fairly for USDOT-assisted work.
When a project manager sees a scope change proposed partway through design, what is the best first step?
Answer: Assess its effect on schedule, cost, environmental documents, and risk through the change-control process before approving
Formal change control looks at a change's effects before it is approved, which prevents scope creep.
How many highway divisions does NCDOT use to manage project delivery and maintenance across the state?
Answer: 14
NCDOT is organized into 14 highway divisions that cover North Carolina's 100 counties.
In a CPM network, what is a finish-to-start relationship?
Answer: The successor cannot start until the predecessor finishes
Finish-to-start, the most common dependency, means the successor begins only after the predecessor is complete.
How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy
Sources & references
Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy
- connect.ncdot.gov — Registration, fees, retake policy, test delivery, eligibility, renewal, score release, passing score, score validity, retake fee · verified Oct 2026