Project Management Flashcards
7 cards from real NCDOT practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 7 Project Management flashcards as text
Under the National Environmental Policy Act (NEPA), which document class is used for federally funded projects expected to have significant environmental impacts?
Answer: Environmental Impact Statement
An EIS is required when a federal action is expected to significantly affect the environment.
A change to the contract's scope, price, or time that both NCDOT and the contractor agree to is usually documented through a:
Answer: Supplemental Agreement
Supplemental agreements formally change contract terms such as scope, quantities, or time.
Which federal program sets participation goals for small firms owned by socially and economically disadvantaged individuals on USDOT-funded projects?
Answer: Disadvantaged Business Enterprise (DBE)
The DBE program (49 CFR Part 26) sets participation goals on USDOT-assisted contracts.
A Schedule Performance Index (SPI) of 1.10 indicates that the project is:
Answer: Ahead of schedule
SPI = EV/PV, and a value above 1.0 means more work has been done than planned.
Before the construction letting, which activity must usually be finished so the contractor has legal access to the work area?
Answer: Right-of-way acquisition
Right-of-way must be acquired or certified before letting so the contractor can legally occupy the site.
Which tool best shows who is Responsible, Accountable, Consulted, and Informed for each project task?
Answer: RACI matrix
A RACI matrix assigns the roles for each deliverable or task.
Federal Buy America requirements for federal-aid highway projects mainly apply to which materials?
Answer: Steel and iron products
FHWA Buy America rules have long required domestically produced steel and iron on federal-aid highway projects.
How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy
Sources & references
Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy
- connect.ncdot.gov — Registration, fees, retake policy, test delivery, eligibility, renewal, score release, passing score, score validity, retake fee · verified Oct 2026