Construction and Evaluation Flashcards

6 cards from real NCARB practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 6 Construction and Evaluation flashcards as text
  1. What is the primary purpose of shop drawings submitted by a contractor?

    Answer: To show how the contractor will fabricate or install specific components

    Shop drawings illustrate contractor-specific fabrication and installation details for approval, but they do not supersede the contract documents.

  2. Under AIA A201, who bears the cost of correcting defective work discovered after final payment?

    Answer: The Contractor, during the one-year correction period

    AIA A201 obligates the contractor to correct defective work for one year after substantial completion at no cost to the owner.

  3. Which delivery method allows the owner to overlap design and construction phases to compress the schedule?

    Answer: Fast-Track Construction Management

    Fast-track construction management allows early construction packages to be bid and built while later design phases are still ongoing, compressing the overall schedule.

  4. A contractor's Schedule of Values is primarily used for what purpose?

    Answer: To allocate the contract sum across work components for progress payment applications

    The Schedule of Values breaks the contract sum into work components so the architect can evaluate progress payment applications accurately.

  5. What document does the architect issue when a minor change in the work is needed and does not affect contract sum or time?

    Answer: Architect's Supplemental Instruction (ASI)

    An ASI authorizes minor changes that have no effect on contract sum or contract time, and does not require contractor agreement.

  6. Which test is typically used to verify the compressive strength of concrete on a construction project?

    Answer: Cylinder compression test

    Concrete cylinder compression tests confirm that hardened concrete meets the specified 28-day compressive strength requirements.

How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy

Sources & references

Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

  1. ncarb.org — Test delivery, eligibility, exam format, passing score, renewal, score release, time limit, score validity, fees, retake fee · verified Oct 2026