NASCLA Lien Laws and Payment Procedures 1 — Questions and Answers
Question 1: What is a 'mechanic's lien' in construction?
- A lien placed on a contractor's tools by a creditor
- A legal claim against a property by unpaid contractors, subcontractors, or suppliers for work or materials provided (Correct answer)
- A lien placed by a mechanic on a vehicle repaired on the job site
- A court order freezing a contractor's bank account
Correct answer: A legal claim against a property by unpaid contractors, subcontractors, or suppliers for work or materials provided
A mechanic's lien (also called a construction lien) is a legal claim placed against the property by unpaid parties who contributed labor or materials, giving them a security interest in the property.
Question 2: Who has the right to file a mechanic's lien in most states?
- Only the general contractor
- General contractors, subcontractors, material suppliers, and sometimes equipment renters who went unpaid (Correct answer)
- Only licensed contractors with more than 5 years experience
- Only parties with a direct contract with the property owner
Correct answer: General contractors, subcontractors, material suppliers, and sometimes equipment renters who went unpaid
In most states, any party who provides labor or materials to improve a property — including subcontractors and material suppliers — has the right to file a mechanic's lien if unpaid.
Question 3: What is a 'preliminary notice' (also called a pre-lien notice) in construction lien law?
- A notice sent to begin construction
- A written notice sent to the owner early in the project informing them of the sender's potential lien rights (Correct answer)
- A notice filed with the court before a lawsuit
- A warning letter sent to a subcontractor about performance issues
Correct answer: A written notice sent to the owner early in the project informing them of the sender's potential lien rights
A preliminary notice is a statutory notice that subcontractors and suppliers must typically send to the property owner (and sometimes lender) early in the project to preserve their lien rights.
Question 4: What happens if a contractor fails to record (file) a mechanic's lien within the statutory deadline?
- They can still file the lien with a late fee
- They permanently lose their lien rights on that project (Correct answer)
- They can file the lien in federal court instead
- The owner must waive all payment objections
Correct answer: They permanently lose their lien rights on that project
Missing the statutory deadline to record a mechanic's lien permanently extinguishes that party's lien rights, leaving them without the security interest in the property.
Question 5: Which of the following would a 'conditional lien waiver' indicate?
- The lien has been unconditionally released upon signing
- The lien release is conditioned upon the receipt of a specific payment — if payment doesn't clear, the lien rights are preserved (Correct answer)
- The contractor waives all future lien rights on all projects
- The subcontractor releases rights for past and future work unconditionally
Correct answer: The lien release is conditioned upon the receipt of a specific payment — if payment doesn't clear, the lien rights are preserved
A conditional lien waiver releases lien rights only upon the condition that a specified payment is actually received and clears, protecting the recipient if the payment fails.
Question 6: What is a 'stop payment notice' in construction law?
- A notice from the bank to stop a contractor's check
- A statutory remedy allowing unpaid subcontractors and suppliers to demand that funds be withheld from the general contractor until they are paid (Correct answer)
- A stop-work order issued by a building inspector
- A notice to stop purchasing materials for a project
Correct answer: A statutory remedy allowing unpaid subcontractors and suppliers to demand that funds be withheld from the general contractor until they are paid
A stop payment notice is a statutory tool available in some states that allows unpaid subcontractors and suppliers to direct the owner or lender to withhold contract funds from the general contractor.
What is a 'mechanic's lien' in construction?