What is the purpose of a 'construction budget' versus a 'project estimate'?
-
A
They are identical documents with different names
-
B
An estimate is used for bidding; a budget is used internally to control and track actual project spending
-
C
A budget is prepared by the owner; an estimate by the contractor
-
D
An estimate is prepared after construction; a budget before