A field inspector notices that deployed TTC devices have been knocked over and not replaced during active work. What is the correct action?
-
A
Document the deficiency and report it at the next weekly meeting
-
B
Immediately notify the contractor to restore devices and halt work if safety is compromised
-
C
Allow work to continue since devices are only a recommendation
-
D
Replace the devices personally without notifying the contractor