What are the key steps in a Lockout/Tagout (LOTO) procedure before performing maintenance?
-
A
Just turn off the switch and start working
-
B
Notify affected employees, shut down, isolate all energy sources, apply locks and tags, release stored energy, and verify zero energy state before work begins
-
C
Only lock the main breaker
-
D
Tag the equipment and start work immediately