When evaluating a foreign direct investment project, the 'adjusted present value' (APV) method separates project value into:
-
A
Operating cash flows discounted at WACC plus terminal value
-
B
Base-case NPV assuming all-equity financing plus PV of financing side effects
-
C
Nominal and real cash flow components
-
D
Pre-tax and post-tax cash flow streams