MHIC Knowledge 5 — Questions and Answers
Question 1: Under Maryland's Home Improvement Law, which of the following projects is EXEMPT from MHIC licensing requirements?
- Adding a deck to a single-family home
- Replacing all windows in a condo unit
- New construction of a residential building (Correct answer)
- Installing a new HVAC system in an existing home
Correct answer: New construction of a residential building
New construction is excluded from MHIC jurisdiction; the license applies only to improvement of existing residential structures.
Question 2: A contractor's MHIC license number must appear on all of the following EXCEPT:
- Written contracts
- Advertisements
- Vehicle signage
- Worker safety plans (Correct answer)
Correct answer: Worker safety plans
Maryland requires the license number on contracts and advertisements but does not mandate it on internal safety documentation.
Question 3: A homeowner wants to cancel a home improvement contract signed at their residence. Under Maryland's right-of-rescission rule, how long does the homeowner have?
- 24 hours
- 3 business days (Correct answer)
- 5 business days
- 7 calendar days
Correct answer: 3 business days
Maryland law gives homeowners three business days to rescind a home improvement contract signed in their home.
Question 4: Which action would most likely result in suspension or revocation of an MHIC license?
- Filing a permit one day late
- Abandoning a project without legal justification (Correct answer)
- Hiring a subcontractor without written notice to the homeowner
- Using subcontractors who are not individually licensed
Correct answer: Abandoning a project without legal justification
Abandoning a contracted project without cause is a primary ground for disciplinary action under Maryland home improvement law.
Question 5: In Maryland, who is responsible for ensuring that the required building permits are obtained before home improvement work begins?
- The homeowner
- The licensed contractor (Correct answer)
- The local building department
- The MHIC
Correct answer: The licensed contractor
The licensed contractor bears the legal obligation to secure all necessary permits prior to starting work.
Question 6: What minimum information must a Maryland home improvement contract include regarding project completion?
- An exact completion date only
- Approximate start and completion dates (Correct answer)
- A penalty clause for delays
- A notarized schedule of milestones
Correct answer: Approximate start and completion dates
Maryland law requires the contract to state approximate start and completion dates for the work.
Question 7: A Maryland contractor is accused of a home improvement violation. Which agency has primary jurisdiction to investigate and adjudicate the complaint?
- Maryland Attorney General's Consumer Protection Division
- Maryland Home Improvement Commission (MHIC) (Correct answer)
- Maryland Department of Labor
- Local county licensing board
Correct answer: Maryland Home Improvement Commission (MHIC)
The MHIC is the primary state agency authorized to investigate complaints against and discipline licensed home improvement contractors.
Under Maryland's Home Improvement Law, which of the following projects is EXEMPT from MHIC licensing requirements?