Contracts and Estimating Flashcards
7 cards from real MHIC practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 7 Contracts and Estimating flashcards as text
Under Maryland Home Improvement Law, what is the maximum number of days a homeowner has to cancel a home improvement contract after signing?
Answer: 3 business days
Maryland law grants homeowners a 3-business-day right of rescission for home improvement contracts signed at their residence.
A contractor's written estimate for a roofing job comes in at $9,800, but the final bill is $12,500. What is the most likely legal issue?
Answer: The contractor violated the Maryland Consumer Protection Act by exceeding the estimate without written authorization
Significant cost overruns beyond a written estimate without prior written change orders can constitute a deceptive trade practice under Maryland law.
Which contract clause protects a contractor if unforeseen site conditions (e.g., hidden mold or rot) substantially increase the project cost?
Answer: Unforeseen conditions clause
An unforeseen conditions clause allows the contractor to seek additional compensation when hidden defects materially change the scope of work.
When preparing a materials estimate, a contractor should add a waste factor to account for cuts and defects. What typical waste factor is used for ceramic tile installations?
Answer: 10–15%
A 10–15% waste factor is standard for ceramic tile to account for cuts, breakage, and pattern matching.
A Maryland MHIC contract must include the contractor's license number. Where must it appear?
Answer: On the face of the contract
Maryland law requires the MHIC license number to appear prominently on the face of every home improvement contract.
A homeowner requests several add-ons mid-project. The best way for a contractor to document and price these changes is to use a:
Answer: Written change order signed by both parties before the work begins
A signed change order executed before the additional work begins protects both parties and is required by Maryland home improvement regulations.
If a subcontractor is not paid by the general contractor, what Maryland legal remedy can the subcontractor use against the homeowner's property?
Answer: File a mechanic's lien
Under Maryland law, unpaid subcontractors and suppliers may file a mechanic's lien against the improved property within prescribed deadlines.
How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy
Sources & references
Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy