A program manager is using Integrated Master Schedule (IMS) with Earned Value Management (EVM). The Cost Performance Index (CPI) is 0.78. This means:
-
A
The project will finish 22% ahead of schedule
-
B
The project is getting $0.78 of value for every $1.00 spent
-
C
The project has spent 78% of its total budget
-
D
The project team is 22% understaffed