A project manager notices that a critical path activity is running two weeks behind schedule. Which response is most appropriate?
-
A
Ignore it and hope the team catches up
-
B
Crash the schedule by adding resources to critical path tasks
-
C
Extend the project deadline immediately
-
D
Remove scope from non-critical activities