A new potable water system has been installed in a commercial building. According to the IPC, which of the following is an acceptable method for disinfection before the system is put into service?
-
A
Flushing the system with hot water at 140°F for at least 30 minutes.
-
B
Filling the system with a solution containing at least 25 ppm of chlorine and letting it stand for 12 hours.
-
C
Flushing the system thoroughly with clean, potable water until all visible debris is removed.
-
D
Filling the system with a solution containing at least 50 ppm of chlorine and letting it stand for 24 hours.