Which project delivery method places the construction manager 'at risk,' meaning they guarantee a maximum price and bear cost overruns above that amount?
-
A
Construction Manager as Advisor (CMA)
-
B
Construction Manager at Risk (CMAR)
-
C
Design-Bid-Build
-
D
Integrated Project Delivery (IPD)