A client verbally instructs an architect to proceed with additional services. Best practice requires the architect to:
-
A
Proceed immediately to maintain client goodwill
-
B
Document the instruction and issue a written amendment before proceeding
-
C
Add the cost to the final invoice without notifying the client in advance
-
D
Refuse the work until a new contract is signed from scratch