Which Architect's Supplemental Instruction (ASI) scenario would be appropriate for a change that involves NO cost or time adjustment?
-
A
Substituting a lower-cost material at the contractor's request
-
B
Clarifying ambiguous dimensions on a drawing without changing scope
-
C
Adding a new program element requested by the owner
-
D
Changing structural systems mid-construction