Lean Six Sigma Yellow Belt Certification The Improve Phase 2 — Questions and Answers
Question 1: A team uses a Pugh Concept Selection Matrix to evaluate solutions. What is the primary purpose of this tool?
- To document root causes of defects
- To compare multiple solution alternatives against weighted criteria (Correct answer)
- To map the current state value stream
- To calculate process sigma levels
Correct answer: To compare multiple solution alternatives against weighted criteria
The Pugh matrix scores competing solutions against evaluation criteria, helping teams select the best option objectively.
Question 2: During a kaizen event, the team identifies a process step that adds no value. According to Lean principles, what should they do first?
- Automate the step to reduce cost
- Eliminate the step if possible (Correct answer)
- Move the step to a different department
- Add a control chart to monitor the step
Correct answer: Eliminate the step if possible
Lean's first priority is to eliminate non-value-added steps entirely before considering optimization or automation.
Question 3: A solution pilot is run on one production line before full rollout. What does the pilot primarily validate?
- That the root cause was correctly identified
- That the solution is feasible and achieves the desired improvement (Correct answer)
- That the control plan is complete
- That all stakeholders have signed off
Correct answer: That the solution is feasible and achieves the desired improvement
A pilot tests solution feasibility and effectiveness at small scale before committing to full implementation.
Question 4: Which improvement tool is best suited for reducing changeover time between product runs?
- FMEA
- SMED (Single-Minute Exchange of Die) (Correct answer)
- Regression analysis
- Box-and-whisker plot
Correct answer: SMED (Single-Minute Exchange of Die)
SMED is a Lean technique specifically designed to reduce equipment changeover and setup times.
Question 5: A process improvement reduces average cycle time from 12 minutes to 8 minutes. What is the percentage improvement?
- 25%
- 33% (Correct answer)
- 50%
- 67%
Correct answer: 33%
The reduction is 4 minutes from a baseline of 12 minutes: (4/12) × 100 = 33.3% improvement.
Question 6: In the Improve phase, what is the purpose of a risk assessment before implementing a solution?
- To identify which employees resist the change
- To anticipate potential failure modes and plan mitigation actions (Correct answer)
- To calculate the return on investment
- To update the project charter
Correct answer: To anticipate potential failure modes and plan mitigation actions
Risk assessment (often via FMEA) identifies what could go wrong with the solution so mitigation plans can be prepared in advance.
Question 7: A team implements 5S in a work area. Which step involves keeping the work area clean and identifying problems through cleanliness?
- Sort
- Set in Order
- Shine (Correct answer)
- Standardize
Correct answer: Shine
Shine (the third S) focuses on cleaning the work area and using cleanliness to expose abnormal conditions like leaks or damage.
A team uses a Pugh Concept Selection Matrix to evaluate solutions.
What is the primary purpose of this tool?