  1. In the Improve phase, a Force Field Analysis is used primarily to:

    Answer: Identify and balance the driving forces and restraining forces surrounding a proposed change

    Force Field Analysis, developed by Kurt Lewin, visually separates the forces pushing toward a change (drivers) from those pushing against it (restrainers), helping the team plan how to amplify drivers and weaken barriers before implementation.

  2. Poka-Yoke devices are incorporated during the Improve phase primarily to:

    Answer: Prevent errors from occurring or detect them immediately before they become defects

    Poka-Yoke (mistake-proofing) mechanisms are designed either to make errors physically impossible (prevention) or to signal an error the instant it occurs (detection), eliminating defects at the source rather than catching them downstream.

  3. A full factorial designed experiment differs from a fractional factorial design in that it:

    Answer: Tests every possible combination of factor levels, estimating all main effects and all interactions

    A full factorial design runs all possible combinations of the chosen factor levels, providing complete information on every main effect and every interaction, but at the cost of more experimental runs compared to fractional alternatives.

  4. When a Green Belt calculates the length of time required for cumulative project savings to equal the initial implementation cost, they are computing the:

    Answer: Payback period

    The payback period measures how long it takes for the accumulated financial benefits of an improvement to recover its upfront cost, and is a common, easy-to-communicate financial justification metric in Lean Six Sigma projects.

  5. A Kaizen event conducted during the Improve phase is best characterized as:

    Answer: A focused, short-duration team effort (typically three to five days) to rapidly implement targeted process improvements

    Kaizen events (also called Kaizen blitzes or rapid improvement workshops) concentrate a cross-functional team on a specific process area for a brief, intensive period to design and implement improvements immediately, compressing months of change into days.

  6. In a designed experiment, an interaction effect between two factors (A and B) indicates that:

    Answer: The effect of factor A on the response variable changes depending on the level at which factor B is set

    An interaction effect means the two factors are not independent in their influence: the magnitude or direction of one factor's impact on the output shifts based on where the other factor is set, so each factor cannot be interpreted in isolation when interactions are present.