Lean Six Sigma Green Belt Define Phase Concepts 1 Flashcards

6 cards from real Lean Six Sigma Green Belt Certification practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 6 Lean Six Sigma Green Belt Define Phase Concepts 1 flashcards as text
  1. What distinguishes a business case from a problem statement in a Six Sigma project charter?

    Answer: The business case justifies the financial and strategic value of the project; the problem statement describes what is wrong and its impact

    A business case explains WHY the project deserves organizational resources by linking it to strategic or financial value, while the problem statement describes WHAT is wrong, how it is measured, and its impact — without proposing causes or solutions.

  2. In the Define phase, a RACI matrix is primarily used to:

    Answer: Clarify team member roles and accountability for project activities

    RACI (Responsible, Accountable, Consulted, Informed) is a responsibility-assignment tool used in the Define phase to ensure every project task has a clear owner and that all stakeholders understand their involvement.

  3. Which of the following best describes a well-written problem statement in a Six Sigma project charter?

    Answer: It quantifies the problem with baseline data, describes its impact, and avoids assigning blame or solutions

    A strong problem statement is fact-based and measurable (e.g., 'defect rate is currently 12%'), describes business impact, and deliberately excludes root causes or solutions so the team investigates with an open mind.

  4. The Kano model, sometimes applied during VOC analysis in the Define phase, classifies customer requirements into three main categories. Which set correctly names them?

    Answer: Must-be, performance, and excitement (delighter) attributes

    The Kano model separates requirements into Must-be (basic expectations whose absence causes dissatisfaction), Performance (more is better, linearly linked to satisfaction), and Excitement/Delighter features (unexpected extras that create delight) to help teams prioritize CTQs.

  5. What is the primary purpose of a tollgate review at the end of the Define phase?

    Answer: To confirm that the team has clearly defined the problem, scope, and goals and is ready to proceed to Measure

    A Define tollgate is a structured checkpoint where the project sponsor and leadership confirm that the charter, problem statement, scope, goals, and team are sound before the team invests effort in data collection during the Measure phase.

  6. In the Define phase, a high-level process map (often called an 'As-Is' map) is most commonly used to:

    Answer: Establish the boundaries, key process steps, and handoff points of the process under study

    The As-Is high-level process map — often a SIPOC or top-level flowchart — gives the team and stakeholders a shared understanding of the current process boundaries, major steps, and where value is transferred, forming the foundation for more detailed analysis in later phases.