Lean Six Sigma Black Belt Certification Lean Enterprise Principles 3 — Questions and Answers
Question 1: In lean enterprise, which type of waste specifically refers to unnecessary movement of workers within a work area?
- Transportation
- Motion (Correct answer)
- Overprocessing
- Waiting
Correct answer: Motion
Motion waste refers to unnecessary physical movements of workers (reaching, bending, walking) that do not add value to the product.
Question 2: A lean enterprise team applies 'heijunka' to their production schedule. What does heijunka primarily accomplish?
- Eliminates all setup time between products
- Levels production volume and mix over time (Correct answer)
- Reduces defect rates to zero
- Identifies the process bottleneck
Correct answer: Levels production volume and mix over time
Heijunka levels production by smoothing out volume and product mix variations, preventing overburden and uneven workloads.
Question 3: Which lean principle emphasizes going to the actual place where work is done to observe and understand the current state?
- Poka-yoke
- Gemba (Correct answer)
- Hoshin kanri
- Catchball
Correct answer: Gemba
Gemba (Japanese for 'the real place') is the practice of going to where value is created to directly observe processes and identify waste.
Question 4: In the context of lean enterprise, 'muri' refers to which category of operational problem?
- Waste
- Unevenness
- Overburden (Correct answer)
- Defects
Correct answer: Overburden
Muri refers to overburden — unreasonable stress placed on workers or machines that leads to breakdowns, errors, and safety issues.
Question 5: A lean Black Belt wants to reduce changeover time between product variants. Which technique is specifically designed for this purpose?
- SMED (Correct answer)
- 5S
- TPM
- FMEA
Correct answer: SMED
Single-Minute Exchange of Die (SMED) is a lean technique that reduces changeover time to less than 10 minutes by converting internal to external setup tasks.
Question 6: In a lean value stream map, a 'push' arrow indicates that material is being:
- Pulled based on actual downstream consumption
- Moved based on a schedule or forecast regardless of downstream need (Correct answer)
- Stored in a supermarket for pull replenishment
- Transported by external logistics
Correct answer: Moved based on a schedule or forecast regardless of downstream need
A push arrow shows that material is moved or produced based on a schedule or forecast, not on actual downstream demand signals.
Question 7: Which lean enterprise concept directly supports the idea that quality should be built into the process rather than inspected in at the end?
- Just-in-Time
- Jidoka (Correct answer)
- Kaizen
- Kanban
Correct answer: Jidoka
Jidoka builds quality into the process by stopping production when defects occur, preventing defective products from advancing downstream.
In lean enterprise, which type of waste specifically refers to unnecessary movement of workers within a work area?