Define Phase: Project Charter Flashcards
7 cards from real Lean Six Sigma Black Belt Certification practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 7 Define Phase: Project Charter flashcards as text
Which section of a project charter quantifies the financial impact of successfully completing the project?
Answer: Business case
The business case section quantifies the financial and strategic value that justifies the investment in the project.
A project charter goal statement should be written using which framework to ensure it is measurable and time-bound?
Answer: SMART
SMART goals are Specific, Measurable, Achievable, Relevant, and Time-bound, making them ideal for project charter goal statements.
In a Lean Six Sigma project charter, the 'entitlement' of a process refers to:
Answer: The theoretical best performance the process can achieve
Entitlement is the best performance a process can theoretically achieve given its current design, often used to set the project goal.
When a Black Belt discovers mid-charter development that the project scope is too broad, the best corrective action is to:
Answer: Narrow the scope and re-align with the sponsor
Narrowing scope and re-aligning with the sponsor ensures the project is feasible and maintains sponsor commitment before work begins.
Which charter element formally documents who has decision-making authority over project resources and direction?
Answer: Team roles and responsibilities
The team roles and responsibilities section defines authority levels, including who is the sponsor, Black Belt, and team members.
A project charter's problem statement should avoid which of the following?
Answer: Identifying the root cause of the problem
The problem statement describes what is wrong and its impact; identifying root cause is the job of the Analyze phase, not the Define phase.
The primary purpose of obtaining a sponsor's signature on the project charter is to:
Answer: Formally authorize the project and commit organizational resources
Sponsor signature formally authorizes the project, commits resources, and signals organizational support for the team's work.
Written and edited by Nathan Beja, founder of Practice Test Geeks, with AI assistance. Exam facts are checked against the official sources linked below. Editorial policy
Sources & references
Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy
- iassc.org — Eligibility, fees, exam format, passing score, time limit, score validity, test delivery, retake policy · verified Oct 2026
- peoplecert.org — Test dates · verified Oct 2026