Define Phase: Project Charter Flashcards

7 cards from real Lean Six Sigma Black Belt Certification practice questions. Tap to flip, then mark Knew It or Still Learning โ€” missed cards come back until you master them.

Read the first 7 Define Phase: Project Charter flashcards as text
  1. Which section of a project charter quantifies the financial impact of successfully completing the project?

    Answer: Business case

    The business case section quantifies the financial and strategic value that justifies the investment in the project.

  2. A project charter goal statement should be written using which framework to ensure it is measurable and time-bound?

    Answer: SMART

    SMART goals are Specific, Measurable, Achievable, Relevant, and Time-bound, making them ideal for project charter goal statements.

  3. In a Lean Six Sigma project charter, the 'entitlement' of a process refers to:

    Answer: The theoretical best performance the process can achieve

    Entitlement is the best performance a process can theoretically achieve given its current design, often used to set the project goal.

  4. When a Black Belt discovers mid-charter development that the project scope is too broad, the best corrective action is to:

    Answer: Narrow the scope and re-align with the sponsor

    Narrowing scope and re-aligning with the sponsor ensures the project is feasible and maintains sponsor commitment before work begins.

  5. Which charter element formally documents who has decision-making authority over project resources and direction?

    Answer: Team roles and responsibilities

    The team roles and responsibilities section defines authority levels, including who is the sponsor, Black Belt, and team members.

  6. A project charter's problem statement should avoid which of the following?

    Answer: Identifying the root cause of the problem

    The problem statement describes what is wrong and its impact; identifying root cause is the job of the Analyze phase, not the Define phase.

  7. The primary purpose of obtaining a sponsor's signature on the project charter is to:

    Answer: Formally authorize the project and commit organizational resources

    Sponsor signature formally authorizes the project, commits resources, and signals organizational support for the team's work.