Lean Six Sigma Black Belt Certification FREE Lean Six Sigma Black Belt Project and Team Management Questions and Answers 2 — Questions and Answers
Question 1: Which tool is MOST appropriate for a Black Belt to use when identifying all potential stakeholders and their influence on a Lean Six Sigma project?
- Stakeholder analysis matrix (Correct answer)
- Project charter
- SIPOC diagram
- Communication plan
Correct answer: Stakeholder analysis matrix
A stakeholder analysis matrix maps each stakeholder's level of influence and interest, helping the Black Belt prioritize engagement strategies.
Question 2: During the Define phase, a Black Belt discovers that two functional managers disagree on the project scope. What is the BEST course of action?
- Escalate immediately to the Champion
- Facilitate a meeting to align scope using data and the project charter (Correct answer)
- Choose the scope preferred by the higher-ranking manager
- Narrow the scope to avoid the conflict entirely
Correct answer: Facilitate a meeting to align scope using data and the project charter
A Black Belt should use facilitation skills and objective data to resolve scope disagreements before escalating to leadership.
Question 3: What is the PRIMARY purpose of a team ground rules document in a Lean Six Sigma project?
- To document technical requirements for the project
- To establish expected behaviors and meeting norms for the team (Correct answer)
- To assign specific deliverables to each team member
- To define the project timeline and milestones
Correct answer: To establish expected behaviors and meeting norms for the team
Ground rules set behavioral expectations such as attendance, participation, and decision-making protocols to ensure productive teamwork.
Question 4: A Black Belt notices that a subject matter expert on the team consistently dominates discussions, preventing quieter members from contributing. Which technique is MOST effective?
- Remove the dominant member from the team
- Use round-robin facilitation to ensure equal input (Correct answer)
- Send an anonymous survey after each meeting
- Allow the behavior since the expert has valuable knowledge
Correct answer: Use round-robin facilitation to ensure equal input
Round-robin facilitation systematically gives every team member an opportunity to speak, balancing participation without singling anyone out.
Question 5: In Tuckman's model of team development, which stage is characterized by team members beginning to resolve conflicts and establish effective working relationships?
- Forming
- Storming
- Norming (Correct answer)
- Performing
Correct answer: Norming
The Norming stage is when teams resolve earlier conflicts, develop cohesion, and agree on working norms and processes.
Question 6: A Black Belt is managing a project with team members from three different time zones. Which approach BEST maintains team engagement and project momentum?
- Require all members to attend meetings at the Black Belt's local time
- Rotate meeting times and use asynchronous collaboration tools for updates (Correct answer)
- Assign all critical tasks to co-located team members only
- Hold meetings only when all members can attend simultaneously
Correct answer: Rotate meeting times and use asynchronous collaboration tools for updates
Rotating meeting times shares the inconvenience fairly while asynchronous tools keep distributed team members informed and engaged between meetings.