LARE Project and Construction Management Flashcards
7 cards from real LARE practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 7 LARE Project and Construction Management flashcards as text
During earthwork, a contractor encounters soil with a swell factor of 25%. If 800 bank cubic yards (BCY) are excavated, how many loose cubic yards (LCY) must be hauled away?
Answer: 1,000 LCY
Loose volume = Bank volume × (1 + swell factor) = 800 × 1.25 = 1,000 LCY; swell increases volume when soil is excavated and loosened.
A project specification requires imported topsoil to have a minimum organic matter content of 5% by weight. The contractor submits a soil test showing 3.8% organic matter and requests a waiver. What is the most appropriate response?
Answer: Reject the soil because it does not meet the minimum specification requirement
Specifications establish minimum performance standards; a soil failing to meet those standards should be rejected unless a formal specification modification is issued by the landscape architect.
What is the primary purpose of a construction observation site visit by the landscape architect?
Answer: To observe work in progress and determine if it generally conforms to the contract documents
Observation (not supervision) involves the LA periodically observing work to evaluate general conformance with the contract documents, not directing means and methods, which is the contractor's responsibility.
A landscape architect is preparing a cost estimate at the schematic design phase. Which estimating method is most appropriate at this stage?
Answer: Square footage or parametric estimate
Parametric or square footage estimates are appropriate at schematic design when insufficient design detail exists for unit price or quantity survey approaches.
A landscape contractor installs irrigation pipe at 18 inches depth instead of the specified 24 inches in a freeze-prone climate. The landscape architect discovers this during an observation visit. What is the correct course of action?
Answer: Issue a non-conformance notice and require the contractor to reinstall at the specified depth
Non-conforming work that does not meet specifications must be rejected and corrected; in freeze-prone areas, inadequate burial depth will cause pipe damage, creating owner liability.
Which scheduling technique shows task durations and overlaps on a horizontal bar chart without explicitly showing task dependencies?
Answer: Gantt chart
A Gantt chart displays tasks as horizontal bars against a timeline showing start/end dates and durations, but does not explicitly depict logical dependencies between tasks.
A change order increases the contract sum by $15,000. The contractor's overhead and profit markup allowed by the contract is 15%. What is the contractor's markup on a $15,000 net cost change?
Answer: $2,250
The markup = $15,000 × 0.15 = $2,250; the total change order amount to the owner would be $15,000 + $2,250 = $17,250.
How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy
Sources & references
Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy
- clarb.org — Fees, retake fee, test delivery, eligibility, score release, score validity, retake policy, time limit, passing score, registration deadline · verified Oct 2026