  1. The average end area method is used to calculate earthwork volumes. If Station 0+00 has an end area of 120 sq ft and Station 1+00 has an end area of 200 sq ft, what is the volume in cubic yards?

    Answer: 593 CY

    Volume = ((120 + 200) / 2) × 100 ft = 16,000 cu ft ÷ 27 = 592.6, approximately 593 CY.

  2. When reading a grading plan, a contour line that forms a 'V' shape pointing uphill indicates which topographic feature?

    Answer: A valley or swale

    Contour V-shapes pointing uphill indicate a valley, drainage swale, or stream channel where water flows.

  3. A landscape architect must grade a parking lot so it drains properly. What is the minimum recommended slope for paved surfaces to ensure positive drainage?

    Answer: 0.25%

    A minimum slope of 0.25% (1/4 of 1%) is generally accepted for paved surfaces to achieve positive drainage.

  4. Which of the following soil classifications has the greatest swell factor when excavated, requiring the most adjustment in earthwork calculations?

    Answer: Rock

    Rock has the highest swell factor (up to 30–40%) because blasting and fracturing dramatically increases its volume compared to in-place conditions.

  5. On a grading plan, a designer places a spot elevation of 102.5 at a low point in a parking lot. The nearest catch basin rim elevation is 102.0. This condition will result in:

    Answer: Ponding water at the low point

    If the low point spot elevation (102.5) is higher than the catch basin rim (102.0), water cannot flow into the basin and will pond at the low point.

  6. A retaining wall is needed where a grade change of 6 feet occurs over a horizontal distance of 8 feet. What is the slope of the retained bank?

    Answer: 1.33:1 (H:V)

    Slope expressed as H:V = horizontal ÷ vertical = 8 ÷ 6 = 1.33:1, meaning for every 1.33 feet of horizontal run there is 1 foot of rise.

  7. During earthwork operations, a shrinkage factor of 0.85 means that:

    Answer: 15% more material must be borrowed to achieve the compacted volume needed

    A shrinkage factor of 0.85 means compacted fill occupies only 85% of its bank volume, so 15% more material must be imported to yield the required compacted volume.

How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy

Sources & references

Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

  1. clarb.org — Fees, retake fee, test delivery, eligibility, score release, score validity, retake policy, time limit, passing score, registration deadline · verified Oct 2026